Data Centers: Daily Notes | October 19, 2026

Local governments are weighing data centers: Dover, Dade City and Gilroy move to pause projects, Boulder City puts the question to voters, Mount Pleasant approves a bigger Microsoft campus, and Sioux County and South Annville advance new rules. READ MORE.

Data Centers: Daily Notes | October 19, 2026
Photo by sergey raikin / Unsplash
Your daily digest of Data Center regulatory shifts and decisions.

At A Glance đź”˝

  • Boulder City, Nevada votes on Nov. 3 on whether to allow data centers in the Eldorado Valley Transfer Area, with supporters citing the need for new revenue and opponents warning of strain on power, water and desert tortoise habitat.
  • Mount Pleasant, Wisconsin approved Microsoft’s revised data center site plan, which cuts the project from nine buildings to seven, grows it to about 5.9 million square feet and adds sound mitigation on the west side before it goes to the Village Council.
  • Gilroy, California will consider extending its data center moratorium by 10 months and 15 days in response to resident concerns, though the $2 billion AWS facility already under construction would not be affected.
  • Dover, Delaware passed an 18-month moratorium on AI data center applications so the city can study its grid capacity and survey residents.
  • Dade City, Florida advanced a 12-month moratorium on new data center development on first reading, citing concerns about groundwater and electrical infrastructure.
  • Sioux County, Iowa advanced its data center ordinance on a 4-1 vote at second reading, setting up an Oct. 27 final vote that would lift the county’s moratorium if the ordinance passes.
  • South Annville Township, Pennsylvania passed a data center zoning ordinance with a decommissioning plan and a community benefits agreement, but with lower setbacks and noise limits than residents and the planning commission had asked for.
  • Emporia, Kansas promised a 21-day public review of any development agreement for the proposed digital campus and listed the conditions it wants from any operator, including jobs, protection from utility cost increases and buyouts for nearby property owners.

Boulder, Nevada

Boulder City voters will decide on Nov. 3 whether to make data centers an approved land use in the Eldorado Valley Transfer Area, outside the Multi-species Habitat Conservation Easement.

Data Centers | Boulder City, NV - Official Website
Like many communities nationwide, Boulder City has received an application for a data center to be located southwest of I-11 and US-93. Seperately, there is a ballot issue on land use for data centers in a different portion of the City - that is addressed at www.bcnv.org/elections) We hope this page will provide residents and neighbors with factual information and answers to their questions.

The City Council placed the measure on the ballot Feb. 24 and invited resident volunteers to write the arguments for and against it. Supporters say every proposal would still go through full land-use and leasing review, and argue the city needs new revenue as its subsidized solar leases near expiration. Opponents point out that the city has never rejected an energy project lease, and warn of strain on regional power infrastructure, shared water supplies, and desert tortoise habitat.


Mount Pleasant, Wisconsin

The Mount Pleasant Planning Commission unanimously approved revised site plans for Microsoft’s data center at 12023 Durand Ave., which cut the number of buildings from nine to seven while growing the project to 5,878,080 square feet.

The original design covered 5.2 million square feet, and Community Development Director Samuel Schultz said the total will likely keep shifting as Microsoft refines its plans. The updated layout includes 10 parking lots, internal roads, stormwater ponds, sound walls, and perimeter security fencing. Microsoft said the changes are meant to speed up development and access the added capacity sooner, not scale back its plans. The commission also asked Microsoft to add sound mitigation along the project’s west side, following a July lawsuit from Sturtevant residents over data center noise. The modifications now go to the Village Council, which was scheduled to take them up Oct. 19 at 6 p.m.


Gilroy, California

Gilroy City Council will consider extending its temporary data center moratorium on Monday, with city staff expected to recommend adding 10 months and 15 days to the pause.

The moratorium followed community pushback over water, power, noise, and transparency. Many residents say they never had a chance to weigh in on data center projects and point to the $2 billion Amazon Web Services facility already under construction. That project sits on 56 acres zoned for heavy industrial use and would not be affected by the council’s decision. The meeting starts at 6 p.m., and residents can comment in person or online.


Dover, Delaware

Dover City Council approved an 18-month moratorium on AI data center applications at its Oct. 12 meeting, wrapping up about two months of discussion and deliberation.

Dover passes temporary data center ban
Dover City Council passes a moratorium on AI data centers within city limits.

The pause is meant to keep data centers from putting undue strain on the city’s power infrastructure and to head off any rate increases that strain could cause. Councilwoman Donyale Hall, who brought the measure forward, described it as a temporary and responsible step to protect residents, businesses, utility customers, and future economic development while the city sets clear standards. During the pause, city staff will study whether Dover’s grid and infrastructure can handle the added load of a data center, and the city will run surveys to gauge how residents feel about the facilities.


In case you missed it:
Data Center Moratorium: Reasons, Impacts, and State Policies
Explore the reasoning behind a data center moratorium, its impact to the communities and data center developers, and some states with moratorium bills.

Dade City, Florida

Dade City commissioners approved the first reading of a 12-month moratorium on new data center development within city limits, citing concerns over groundwater and electrical infrastructure.

Dade City Weighs 12-Month Data Center Moratorium
Dade City just took its first step toward banning new data centers for a year.

If adopted on second reading, the pause would block the submission and acceptance of building permits, site plans, development orders, special exception uses, rezonings, and comprehensive plan amendments tied to data centers. Commissioner Kristin Church raised concerns about water use, and Commissioner Scott Black said the city would need to conserve water if data centers came in. The pause gives the city time to decide whether data centers belong in Dade City and to update its comprehensive plan, land development code, and code of ordinances, and it could be lifted early depending on what that review finds.


Sioux County, Iowa

The Sioux County Board of Supervisors advanced its proposed data center ordinance on a 4-1 vote at its second reading, setting up a final reading on Oct. 27.

An Amendment to the Sioux County Zoning Ordinance

Supervisor Dan Altena again cast the lone no vote, while John Degen, Craig Hoftyzer, Jerry Muilenburg and Carl Vande Weerd voted in favor. If the ordinance passes, it takes effect upon publication and the county’s moratorium will be lifted. Zoning director Shane Walter said the language hasn’t changed since the first reading, and any edits would have to go back to the zoning commission for review. The county will set a separate fine schedule for violations, and Vande Weerd said the ordinance also lets the county shut down a data center that falls out of compliance.


South Annville Township, Pennsylvania

South Annville Township supervisors passed Ordinance #10-14-26 to regulate data centers, choosing to pass it now and refine it later as regulations shift.

Read the full ordinance here

The board added a decommissioning plan and a community benefits agreement but kept setbacks and noise limits below what a resident and the planning commission requested, citing the solicitor’s advice on what the township can legally defend. Supervisors said they wanted the ordinance on the books before another data center proposal arrives. The board next meets Wednesday, Nov. 11.


Emporia, Kansas

Emporia city leaders pledged that any development agreement for the proposed digital campus would be posted for 21 days of public review before a commission vote.

Mayor Becky Smith, Commissioner Tammy Ogle, and City Manager Trey Cocking laid out conditions they want any operator to meet, including hundreds of permanent on-site jobs, financial guarantees, protection against utility cost increases, and community benefits from the start. They also floated a voluntary above-market buyout for property owners within 500 feet, along with plans for dust, noise, roads, stormwater, and decommissioning.


📱 Social Buzz

Episode Title: Tesla's historic flying car, and election talk

Episode: The James Show

Listen: https://omny.fm/shows/the-james-parker-podcast/teslas-historic-flying-car-and-election-talk


Strisker Government Officials Dashboard

Trying to keep up with the main players in the STR and Data Center game? Know your council members, commissioners, committee chairs, and key staff that are part of the process.

Create Your Watchlist - 14 Day Free Trial

Stay Updated with Strisker!

Strisker offers tools and features to keep you updated with the Short Term Rental and Data Centers movement across the world.

👍 We’d love your feedback.
Which stories hit? Which ones missed?

We're exploring a new branch of topics centered around Data Centers and want to make it even more useful for you.

✉️ Just reply directly to this email. We read and respond to every message!

-Will McClure
🙋 P.S.
Know someone else who should be reading Daily Notes? Feel free to forward this along. We’re opening a few more spots.

Subscribe to Strisker - Short-Term Rental and Data Center regulations

Don’t miss out on the latest issues. Sign up now to get access to the library of members-only issues.
jamie@example.com
Subscribe